Long-Term Isolations Step

Isolations at the ‘Confirmed Isolated’ Stage (orange box) can be moved into the Long-Term Isolation register, as per the workflow below:

  1. Authorised personnel request that the isolation be moved to the Long-Term Isolation Register.
  2. An approver approves or rejects the request.
  3. If approved, the isolation is now in the Long Term Isolation Register.
  4. As an optional step, authorised users can confirm the long-term isolation – i.e. confirm periodic checks and that the equipment should remain in long-term isolation.
  5. To remove from Long-Term Isolation Register, authorised personnel request removal from Long Term Isolations.
  6. An approver approves or rejects the request.
  7. If approved, the isolation is moved from the long-term isolations register to the list of current isolations, returning to the standard isolations workflow.